State Codes and Statutes

Statutes > Arizona > Title41 > 41-2582

41-2582. Project delivery methods for design and construction services

A. A purchasing agency may procure design services, construction and construction services, as applicable, under any of the following project delivery methods:

1. Design-bid-build.

2. Construction-manager-at-risk.

3. Design-build.

4. Job-order-contracting.

B. For the design-bid-build project delivery method, the director shall procure:

1. Design services pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

2. Construction by competitive sealed bidding, except as otherwise provided in section 41-2532.

C. The director shall procure construction services under the construction-manager-at-risk, design-build and job-order-contracting project delivery methods pursuant to section 41-2535, 41-2536, 41-2537, 41-2578 or 41-2579.

D. The director shall procure design services relating to a construction-manager-at-risk construction services project pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

E. For job-order-contracting construction services projects, if the director does not include design services in the job-order-contracting construction services contract, the director shall procure any design services relating to job-order-contracting construction services projects under the contract pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

State Codes and Statutes

Statutes > Arizona > Title41 > 41-2582

41-2582. Project delivery methods for design and construction services

A. A purchasing agency may procure design services, construction and construction services, as applicable, under any of the following project delivery methods:

1. Design-bid-build.

2. Construction-manager-at-risk.

3. Design-build.

4. Job-order-contracting.

B. For the design-bid-build project delivery method, the director shall procure:

1. Design services pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

2. Construction by competitive sealed bidding, except as otherwise provided in section 41-2532.

C. The director shall procure construction services under the construction-manager-at-risk, design-build and job-order-contracting project delivery methods pursuant to section 41-2535, 41-2536, 41-2537, 41-2578 or 41-2579.

D. The director shall procure design services relating to a construction-manager-at-risk construction services project pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

E. For job-order-contracting construction services projects, if the director does not include design services in the job-order-contracting construction services contract, the director shall procure any design services relating to job-order-contracting construction services projects under the contract pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.


State Codes and Statutes

State Codes and Statutes

Statutes > Arizona > Title41 > 41-2582

41-2582. Project delivery methods for design and construction services

A. A purchasing agency may procure design services, construction and construction services, as applicable, under any of the following project delivery methods:

1. Design-bid-build.

2. Construction-manager-at-risk.

3. Design-build.

4. Job-order-contracting.

B. For the design-bid-build project delivery method, the director shall procure:

1. Design services pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

2. Construction by competitive sealed bidding, except as otherwise provided in section 41-2532.

C. The director shall procure construction services under the construction-manager-at-risk, design-build and job-order-contracting project delivery methods pursuant to section 41-2535, 41-2536, 41-2537, 41-2578 or 41-2579.

D. The director shall procure design services relating to a construction-manager-at-risk construction services project pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.

E. For job-order-contracting construction services projects, if the director does not include design services in the job-order-contracting construction services contract, the director shall procure any design services relating to job-order-contracting construction services projects under the contract pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.