IC 5-30-2
     Chapter 2. General Provisions

IC 5-30-2-1
Validity of design-build contract
    
Sec. 1. A design-build contract awarded as provided in this chapter is valid and enforceable.
As added by P.L.74-2005, SEC.1.

IC 5-30-2-2
Adoption of resolution required
    
Sec. 2. Before entering into a design-build contract under this article for a public project, the governing body of a public agency must adopt a resolution authorizing the use of the design-build contracting method for the public project. The resolution must identify the members of the technical review committee appointed under IC 5-30-4. The governing body must adopt the resolution at a public meeting for which public notice has been provided.
As added by P.L.74-2005, SEC.1.

State Codes and Statutes

Statutes > Indiana > Title5 > Ar30 > Ch2

IC 5-30-2
     Chapter 2. General Provisions

IC 5-30-2-1
Validity of design-build contract
    
Sec. 1. A design-build contract awarded as provided in this chapter is valid and enforceable.
As added by P.L.74-2005, SEC.1.

IC 5-30-2-2
Adoption of resolution required
    
Sec. 2. Before entering into a design-build contract under this article for a public project, the governing body of a public agency must adopt a resolution authorizing the use of the design-build contracting method for the public project. The resolution must identify the members of the technical review committee appointed under IC 5-30-4. The governing body must adopt the resolution at a public meeting for which public notice has been provided.
As added by P.L.74-2005, SEC.1.


State Codes and Statutes

State Codes and Statutes

Statutes > Indiana > Title5 > Ar30 > Ch2

IC 5-30-2
     Chapter 2. General Provisions

IC 5-30-2-1
Validity of design-build contract
    
Sec. 1. A design-build contract awarded as provided in this chapter is valid and enforceable.
As added by P.L.74-2005, SEC.1.

IC 5-30-2-2
Adoption of resolution required
    
Sec. 2. Before entering into a design-build contract under this article for a public project, the governing body of a public agency must adopt a resolution authorizing the use of the design-build contracting method for the public project. The resolution must identify the members of the technical review committee appointed under IC 5-30-4. The governing body must adopt the resolution at a public meeting for which public notice has been provided.
As added by P.L.74-2005, SEC.1.