45-6C-52. Annual report of activities conducted under notice of intent--Information to be included. For each exploration notice of intent held by an operator, an annual report of activities conducted under the notice shall be submitted to the department by January first of each year. Any operator holding more than one notice may submit a single annual report describing activities conducted under all such notices. The annual report shall include the following information:
(1) The total number of drill holes, trenches, bulk sampling sites, or shot holes allowed by the notice;
(2) The total number of drill holes, trenches, bulk sampling sites, or shot holes completed during the previous year under the notice;
(3) The total amount of surface disturbance created as the result of conducting exploration activities under the notice;
(4) The total number of drill or shot holes plugged and reclaimed during the previous year including the method used to plug each hole;
(5) The total amount of surface disturbance reclaimed during the previous year;
(6) The total amount of surface disturbance remaining to be reclaimed;
(7) The total number of drill or shot holes remaining to be plugged and reclaimed; and
(8) A description of the coming year's activities to be conducted under the notice.
The annual report shall be accompanied by a map of sufficient detail to clearly depict the information required in the annual report.

Source: SL 1992, ch 254, § 6.

State Codes and Statutes

Statutes > South-dakota > Title-45 > Chapter-06c > Statute-45-6c-52

45-6C-52. Annual report of activities conducted under notice of intent--Information to be included. For each exploration notice of intent held by an operator, an annual report of activities conducted under the notice shall be submitted to the department by January first of each year. Any operator holding more than one notice may submit a single annual report describing activities conducted under all such notices. The annual report shall include the following information:
(1) The total number of drill holes, trenches, bulk sampling sites, or shot holes allowed by the notice;
(2) The total number of drill holes, trenches, bulk sampling sites, or shot holes completed during the previous year under the notice;
(3) The total amount of surface disturbance created as the result of conducting exploration activities under the notice;
(4) The total number of drill or shot holes plugged and reclaimed during the previous year including the method used to plug each hole;
(5) The total amount of surface disturbance reclaimed during the previous year;
(6) The total amount of surface disturbance remaining to be reclaimed;
(7) The total number of drill or shot holes remaining to be plugged and reclaimed; and
(8) A description of the coming year's activities to be conducted under the notice.
The annual report shall be accompanied by a map of sufficient detail to clearly depict the information required in the annual report.

Source: SL 1992, ch 254, § 6.


State Codes and Statutes

State Codes and Statutes

Statutes > South-dakota > Title-45 > Chapter-06c > Statute-45-6c-52

45-6C-52. Annual report of activities conducted under notice of intent--Information to be included. For each exploration notice of intent held by an operator, an annual report of activities conducted under the notice shall be submitted to the department by January first of each year. Any operator holding more than one notice may submit a single annual report describing activities conducted under all such notices. The annual report shall include the following information:
(1) The total number of drill holes, trenches, bulk sampling sites, or shot holes allowed by the notice;
(2) The total number of drill holes, trenches, bulk sampling sites, or shot holes completed during the previous year under the notice;
(3) The total amount of surface disturbance created as the result of conducting exploration activities under the notice;
(4) The total number of drill or shot holes plugged and reclaimed during the previous year including the method used to plug each hole;
(5) The total amount of surface disturbance reclaimed during the previous year;
(6) The total amount of surface disturbance remaining to be reclaimed;
(7) The total number of drill or shot holes remaining to be plugged and reclaimed; and
(8) A description of the coming year's activities to be conducted under the notice.
The annual report shall be accompanied by a map of sufficient detail to clearly depict the information required in the annual report.

Source: SL 1992, ch 254, § 6.