Reports of well construction or decommissioning.

(1) Any person authorized by this chapter to construct or decommission a well shall furnish a well report to the director within thirty days after the completion of the construction or decommissioning of a well. The director, by rule, shall prescribe the form of the report and the information to be contained therein.

     (2) In the case of a dewatering well project:

     (a) A single well construction report may be submitted for all similar dewatering wells constructed with no significant change in geologic formation; and

     (b) A single well decommissioning report may be submitted for all similar dewatering wells decommissioned that have no significant change in geologic formation.

[2005 c 84 § 3; 1993 c 387 § 8; 1971 ex.s. c 212 § 5.]

State Codes and Statutes

Statutes > Washington > Title-18 > 18-104 > 18-104-050

Reports of well construction or decommissioning.

(1) Any person authorized by this chapter to construct or decommission a well shall furnish a well report to the director within thirty days after the completion of the construction or decommissioning of a well. The director, by rule, shall prescribe the form of the report and the information to be contained therein.

     (2) In the case of a dewatering well project:

     (a) A single well construction report may be submitted for all similar dewatering wells constructed with no significant change in geologic formation; and

     (b) A single well decommissioning report may be submitted for all similar dewatering wells decommissioned that have no significant change in geologic formation.

[2005 c 84 § 3; 1993 c 387 § 8; 1971 ex.s. c 212 § 5.]


State Codes and Statutes

State Codes and Statutes

Statutes > Washington > Title-18 > 18-104 > 18-104-050

Reports of well construction or decommissioning.

(1) Any person authorized by this chapter to construct or decommission a well shall furnish a well report to the director within thirty days after the completion of the construction or decommissioning of a well. The director, by rule, shall prescribe the form of the report and the information to be contained therein.

     (2) In the case of a dewatering well project:

     (a) A single well construction report may be submitted for all similar dewatering wells constructed with no significant change in geologic formation; and

     (b) A single well decommissioning report may be submitted for all similar dewatering wells decommissioned that have no significant change in geologic formation.

[2005 c 84 § 3; 1993 c 387 § 8; 1971 ex.s. c 212 § 5.]