CHAPTER 4 - LABOR AND MATERIALS ON DITCHES, CANALS ANDRESERVOIRS

 

29-4-101. Persons entitled to lien; extent thereof.

 

 

(a) Any person who performs any work or furnishes any materialsfor the construction or improvement of any ditch, canal or reservoir undercontract with the owner or his contractor or subcontractor, on complying withW.S. 29-2-101 through 29-2-109, is entitled to a lien for work done or materialfurnished upon the ditch, canal or reservoir. The lien covers:

 

(i) The right-of-way for the ditch, canal or reservoir;

 

(ii) The pertinent water permits and water rights; and

 

(iii) The reclaimed lands for which the ditch, canal or reservoirwas constructed.

 

29-4-102. Filing of lien statement; enforcement.

 

Anyperson entitled may file a lien statement as provided by W.S. 29-1-101 through29-1-308 and 29-2-101 through 29-2-109 and may enforce his lien in the samemanner.

 

NOTE: Effective7/1/2011, this section will read as follows:

 

29-4-102. Filing of lien statement; enforcement.

 

Anyperson entitled may file a lien statement as provided by W.S. 29-1-103 through29-1-314 and 29-2-101 through 29-2-113 and may enforce his lien in the samemanner.

 

State Codes and Statutes

Statutes > Wyoming > Title29 > Chapter4

CHAPTER 4 - LABOR AND MATERIALS ON DITCHES, CANALS ANDRESERVOIRS

 

29-4-101. Persons entitled to lien; extent thereof.

 

 

(a) Any person who performs any work or furnishes any materialsfor the construction or improvement of any ditch, canal or reservoir undercontract with the owner or his contractor or subcontractor, on complying withW.S. 29-2-101 through 29-2-109, is entitled to a lien for work done or materialfurnished upon the ditch, canal or reservoir. The lien covers:

 

(i) The right-of-way for the ditch, canal or reservoir;

 

(ii) The pertinent water permits and water rights; and

 

(iii) The reclaimed lands for which the ditch, canal or reservoirwas constructed.

 

29-4-102. Filing of lien statement; enforcement.

 

Anyperson entitled may file a lien statement as provided by W.S. 29-1-101 through29-1-308 and 29-2-101 through 29-2-109 and may enforce his lien in the samemanner.

 

NOTE: Effective7/1/2011, this section will read as follows:

 

29-4-102. Filing of lien statement; enforcement.

 

Anyperson entitled may file a lien statement as provided by W.S. 29-1-103 through29-1-314 and 29-2-101 through 29-2-113 and may enforce his lien in the samemanner.

 


State Codes and Statutes

State Codes and Statutes

Statutes > Wyoming > Title29 > Chapter4

CHAPTER 4 - LABOR AND MATERIALS ON DITCHES, CANALS ANDRESERVOIRS

 

29-4-101. Persons entitled to lien; extent thereof.

 

 

(a) Any person who performs any work or furnishes any materialsfor the construction or improvement of any ditch, canal or reservoir undercontract with the owner or his contractor or subcontractor, on complying withW.S. 29-2-101 through 29-2-109, is entitled to a lien for work done or materialfurnished upon the ditch, canal or reservoir. The lien covers:

 

(i) The right-of-way for the ditch, canal or reservoir;

 

(ii) The pertinent water permits and water rights; and

 

(iii) The reclaimed lands for which the ditch, canal or reservoirwas constructed.

 

29-4-102. Filing of lien statement; enforcement.

 

Anyperson entitled may file a lien statement as provided by W.S. 29-1-101 through29-1-308 and 29-2-101 through 29-2-109 and may enforce his lien in the samemanner.

 

NOTE: Effective7/1/2011, this section will read as follows:

 

29-4-102. Filing of lien statement; enforcement.

 

Anyperson entitled may file a lien statement as provided by W.S. 29-1-103 through29-1-314 and 29-2-101 through 29-2-113 and may enforce his lien in the samemanner.