CHAPTER 42. DEFAULT STANDARDS FOR COMMERCIAL SOLAR ENERGY SYSTEMS
- IC 8-1-42-1 Applicability; "solar energy ready community"
- IC 8-1-42-2 "Commercial solar energy system"
- IC 8-1-42-3 "Commercial solar regulation"
- IC 8-1-42-4 "Dwelling"
- IC 8-1-42-5 "Nonparticipating property"
- IC 8-1-42-6 "Permit authority"
- IC 8-1-42-7 "Project owner"
- IC 8-1-42-8 "Unit"
- IC 8-1-42-9 Permit authority responsible for enforcing compliance with standards; authority to adopt less restrictive standards or to waive or make less restrictive existing standards; unit's planning and zoning powers not affected
- IC 8-1-42-10 Setback requirements; highways, collector roads, and local roads; nonparticipating properties; landscape buffer; height restriction; waiver of setback and buffer requirements with consent of nonparticipating property owner
- IC 8-1-42-11 Ground cover; vegetation plan
- IC 8-1-42-12 Fencing
- IC 8-1-42-13 Underground cables; aboveground infrastructure; depth of buried cables; cables and lines outside of project site
- IC 8-1-42-14 Glare minimization; adjacent properties and roadways; vehicular traffic
- IC 8-1-42-15 Signal interference
- IC 8-1-42-16 Sound level limitations; waiver of requirement with consent of owners of adjacent nonparticipating properties
- IC 8-1-42-17 Damage to drainage infrastructure; repair; installation of new infrastructure
- IC 8-1-42-18 Decommissioning and site restoration plan; posting of surety bond or equivalent security; required posting increments; adjustment of bond or security after periodic reevaluation of decommissioning costs; costs to be net of estimated salvage value; project owner's notice of intent to decommission CSE system; ground restoration; project owner's failure to remove project assets; assets allowed to remain in place with landowner's consent
- IC 8-1-42-19 CSE system's failure to generate electricity; presumed abandonment; required removal of project assets; project owner's failure to remove assets; removal of assets by permit authority; recovery of costs
- IC 8-1-42-20 "Force majeure event"; cessation of electricity generation; project owner's notice to permit authority; failure to resume operations; presumed abandonment; project owner's failure to remove assets; removal of assets by permit authority; recovery of costs