(a) New dams.--In issuing permits for the construction or installation of new run-of-the-river dams on the waters of this Commonwealth, the department shall include a permit advisory notifying the permittee of the requirements of this section. The permittee of a new run-of-the-river dam shall mark the areas above and below the dam and on the banks immediately adjacent to the dam with signs and buoys of a design and content determined by the commission to warn the swimming, fishing and boating public of the hazards posed by the dam.

(b) Existing dams.--

(1) (Deleted by amendment).

(1.1) The department shall compile and maintain a current list of existing dams on the waters of this Commonwealth that are run-of-the-river dams. The department shall provide the commission with identifying information about the permittee or owner, location, size and specifications of the run-of-the-river dams annually, unless otherwise requested by the commission. The following shall apply:

(i) Within three months of the discovery of a run-of-the river dam not already inventoried by the department, the department shall notify the permittees and owners of the dam of the requirements of this section in writing.

(ii) Within six months of receiving notification of the requirements of this section from the department, the permittees and owners of run-of-the-river dams shall comply with the requirements of this section to mark the areas above and below the dams and on the banks immediately adjacent to the dams during the time periods of the year required by the commission with signs and buoys of a design and content determined by the commission to warn the swimming, fishing and boating public of the hazards posed by the dam.

(2) If the permittee or owner of a run-of-the-river dam disagrees with the determination of the department, the permittee or owner may appeal the action to the Environmental Hearing Board under section 4 of the act of July 13, 1988 (P.L.530, No.94), known as the Environmental Hearing Board Act, and 2 Pa.C.S. Ch. 5 (relating to practice and procedure) within 30 days of receiving the determination. The Environmental Hearing Board shall reach a decision as soon as practicable. If the decision of the board upholds the determination of the department, the permittee or owner filing the notice shall have three months to comply with this section following the decision.

(b.1) Public information.--Within one year of the effective date of this subsection, the following information shall be published on the department's and commission's publicly accessible Internet websites:

(1) The list compiled and maintained by the department under subsection (b).

(2) A map of this Commonwealth, developed by the department, that shows the locations of all run-of-the-river dams known to the department within this Commonwealth.

(c) Maintenance of signs and buoys.--

(1) It shall be the responsibility of the permittees and owners of run-of-the-river dams to maintain in proper location, legible condition and during the time periods of the year established by the commission signs and buoys installed pursuant to the requirements of this section.

(2) When a permittee or owner learns that signs or buoys installed under this section have been removed or defaced by an act of God or the acts or omissions of third parties other than the permittee or owner, the permittee or owner shall repair or replace the signs or buoys within 15 days unless an extension is requested by the permittee or owner and granted by the commission as a result of conditions during that time make such repair or replacement dangerous to undertake or impracticable to effect, in which case the permittee or owner shall repair or replace the signs or buoys as soon as is reasonably practicable. If a permittee removes any signs or buoys, the permittee or owner shall have five days thereafter to repair or replace the signs or buoys.

(d) Size, content and location of signs and buoys marking run-of-the-river dams.--The commission, after consultation with the department, shall establish requirements for the content and location of signs and buoys to be installed under the authority of this section and the time periods of the year when the signs and buoys shall be required to be in place. The commission shall describe the requirements by notice published in the Pennsylvania Bulletin and may from time to time revise the requirements as circumstances require.

(e) Preemption of Federal law.--Any warning sign or buoy installed and maintained in the areas above or below a run-of-the-river dam or on the banks immediately adjacent to such a dam by a dam permittee or owner in compliance with the requirements of the United States Coast Guard, the Federal Energy Regulatory Commission or any Federal agency having jurisdiction over a run-of-the-river dam shall be deemed to meet the requirements established or imposed by or under this section regarding the placement of warning signs or buoys in said areas.

(f) Standard of care.--A dam permittee or owner who complies with the provisions of this section to mark a dam and who maintains signs and buoys as required by this section shall be deemed to have met the standard of care for warning the public of the hazards posed by the dam.

(g) Regulations.--The commission may promulgate regulations to implement the provisions of this section.

(h) Penalties.--

(1) Any person who fails to comply with subsection (a) or (b) commits a summary offense of the first degree for the first offense and a misdemeanor of the third degree for a subsequent offense. Each 15-day period of noncompliance shall constitute a separate violation.

(2) Any person who fails to comply with subsection (c) or (d) commits a summary offense of the second degree for the first offense and a summary offense of the first degree for a subsequent offense. Each 15-day period of noncompliance shall constitute a separate violation.

(2.1) Any person who fails to comply with subsection (g) commits a summary offense of the third degree.

(2.2) For purposes of paragraphs (1) and (2), each additional 15-day period of noncompliance constitutes a subsequent offense. Each subsequent offense may be separately charged, graded and prosecuted under the applicable paragraph without awaiting adjudication of any preceding offense. Nothing in this paragraph shall relieve the Commonwealth of its burden of proving each offense and the facts necessary to establish its grading or limit the right of a defendant to contest any charge.

(3) Any person who enters an exclusion zone marked under the provisions of this section commits a summary offense of the third degree provided that it shall not be a violation of this section for the permittee or owner and officers of the Commonwealth and local government to enter the exclusion zone for purposes of maintaining the dams and signs and buoys or for enforcement and rescue purposes.

(4) All fines received under this subsection shall be paid into the State Treasury for the use of the Fish Fund or Boat Fund, as appropriate.

(5) The provisions of 18 Pa.C.S. (relating to crimes and offenses) and section 923 (relating to classification of offenses and penalties), insofar as they relate to imprisonment for convictions of summary and misdemeanor offenses, are not applicable to this section.

(i) Definitions.--As used in this section, the following words and phrases shall have the meanings given to them in this subsection:

"Department." The Department of Environmental Protection of the Commonwealth.

"Owner." The person who owns, controls, operates, maintains or manages a run-of-the-river dam regulated by the Department of Environmental Protection pursuant to the act of November 26, 1978 (P.L.1375, No.325), known as the Dam Safety and Encroachments Act.

"Permit." A permit issued by the Department of Environmental Protection pursuant to the act of November 26, 1978 (P.L.1375, No.325), known as the Dam Safety and Encroachments Act.

"Permittee." The person who has been issued a permit by the Department of Environmental Protection to construct, operate or maintain a run-of-the-river dam regulated by the Department of Environmental Protection pursuant to the Dam Safety and Encroachments Act.

"Run-of-the-river dam." A manmade structure which:

(1) is a dam regulated by the Department of Environmental Protection pursuant to the act of November 26, 1978 (P.L.1375, No.325), known as the Dam Safety and Encroachments Act;

(2) is built across or partially across a watercourse and certain flows pass over the dam structure, excluding abutments, to a natural channel downstream; and

(3) the department, in consultation with the commission, determines to have hydraulic characteristics such that at certain flows persons may be caught in the hydraulic roller or boil immediately below the dam.

(June 19, 1998, P.L.702, No.91, eff. Jan. 1, 1999; July 1, 2020, P.L.520, No.39, eff. 60 days; Oct. 22, 2026, P.L.600, No.69, eff. 60 days)

2026 Amendment. Act 69 amended subsecs. (b), (c)(2) and (h)(1), (2) and (3) and the defs. of "owner," "permittee" and "run-of-the-river dam" in subsec. (i) and added subsecs. (b.1) and (h)(2.1) and (2.2).

2020 Amendment. Act 39 amended subsecs. (h)(1) and (2) and (i) and added subsec. (h)(5).

1998 Amendment. Act 91 added section 3510.