28-6951. Five year transportation facilities
construction program; departmental committee


A. The director shall develop a five year transportation facilities construction
program according to the policies established by the board.


B. To aid in the development of the five year transportation facilities
construction program, the director shall appoint a departmental committee that is
responsible to the director. The departmental committee is subject to title 38, chapter
3, article 3.1.


C. The departmental committee shall:


1. Recommend priorities on transportation facilities construction projects to be
constructed by this state that may include any relevant criteria for the development of
priority recommendations for the construction and development of transportation
facilities to be constructed by this state.


2. Update and prepare annually a long-range statewide transportation facilities
construction program covering the following five fiscal years for submission to the board
as follows:


(a) The first year of the five year program shall consist of the highest priority
transportation facilities construction projects that with reasonable certainty can be
advertised for public bidding.


(b) The committee shall group proposed projects for the four remaining years of the
five year program by the year it is estimated construction will begin and in order of
their priorities.


(c) The committee shall provide the estimated cost of the program for each year
that is approximately equal to the revenues estimated to be available for transportation
facilities construction purposes during that year.


3. Review priority changes in or introduction of new projects to a proposed or an
adopted five year program that the board has requested and make recommendations in a
written report to the board on the requested priority changes or introduction of new
projects based on a study of the criteria and policy that establish the priorities of
projects.


4. Review the adopted five year transportation facilities construction program from
time to time during the fiscal year and make recommendations in a written report to the
board for priority changes in or introduction of new projects to the program based on a
study of the criteria and policy that establish the priorities of projects.


5. Fully document its recommendations in the written reports required by this
section.