28-6953. Updated program; annual report


A. Except as provided in subsection C of this section, on or before June 30 of each
year, the board shall:


1. Adopt an updated five year transportation facilities construction program for
the following five fiscal years.


2. File a written report with the director and the governor outlining the updated
program and explaining any priority changes made pursuant to section 28-6955.


3. File a copy of the program with the director of the department of administration
and the state treasurer.


B. On or before the first Monday in August of each year, the board shall prepare
and make available to the public an annual report that summarizes the updated five year
statewide transportation facilities construction program. The report shall contain:


1. The name of each proposed transportation facilities construction project.


2. The anticipated year each project will be advertised for bidding.


3. The location, description and total estimated cost of each project.


4. An explanation of the project's priority.


5. Other data the board deems necessary.


C. Notwithstanding sections 28-304 and 28-6955, the five year transportation
facilities construction program in effect on June 30, 2000, and the regional freeway
program scheduled for completion by 2007 and in effect on June 30, 2000, shall not be
delayed or postponed and shall remain in effect without change in priority or programming
until the projects planned or programmed in the five year transportation facilities
construction program and regional freeway program scheduled for completion by 2007 are
substantially complete.