41-2582. Project delivery methods for design
and construction services


A. A purchasing agency may procure design services, construction and construction
services, as applicable, under any of the following project delivery methods:


1. Design-bid-build.


2. Construction-manager-at-risk.


3. Design-build.


4. Job-order-contracting.


B. For the design-bid-build project delivery method, the director shall procure:


1. Design services pursuant to section 41-2535, 41-2536, 41-2537, 41-2578, 41-2579
or 41-2581.


2. Construction by competitive sealed bidding, except as otherwise provided in
section 41-2532.


C. The director shall procure construction services under the
construction-manager-at-risk, design-build and job-order-contracting project delivery
methods pursuant to section 41-2535, 41-2536, 41-2537, 41-2578 or 41-2579.


D. The director shall procure design services relating to a
construction-manager-at-risk construction services project pursuant to section 41-2535,
41-2536, 41-2537, 41-2578, 41-2579 or 41-2581.


E. For job-order-contracting construction services projects, if the director does
not include design services in the job-order-contracting construction services contract,
the director shall procure any design services relating to job-order-contracting
construction services projects under the contract pursuant to section 41-2535, 41-2536,
41-2537, 41-2578, 41-2579 or 41-2581.