CONTRACTS FOR IMPROVMENT TO REAL PROPERTY (EXCERPT)
Act 57 of 1998

125.1592 Improvement contract exceeding $75,000; provisions.

Sec. 2.

A contract between a contractor and a governmental entity for an improvement that exceeds $75,000.00 shall contain all of the following provisions:

(a) That if a contractor discovers 1 or both of the following physical conditions of the surface or subsurface at the improvement site, before disturbing the physical condition, the contractor shall promptly notify the governmental entity of the physical condition in writing:

(i) A subsurface or a latent physical condition at the site is differing materially from those indicated in the improvement contract.

(ii) An unknown physical condition at the site is of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the improvement contract.

(b) That if the governmental entity receives a notice under subdivision (a), the governmental entity shall promptly investigate the physical condition.

(c) That if the governmental entity determines that the physical conditions do materially differ and will cause an increase or decrease in costs or additional time needed to perform the contract, the governmental entity's determination shall be made in writing and an equitable adjustment shall be made and the contract modified in writing accordingly.

(d) That the contractor cannot make a claim for additional costs or time because of a physical condition unless the contractor has complied with the notice requirements of subdivision (a). The governmental entity may extend the time required for notice under subdivision (a).

(e) That the contractor cannot make a claim for an adjustment under the contract after the contractor has received the final payment under the contract.


History: 1998, Act 57, Eff. Oct. 6, 1998

State Codes and Statutes

Statutes > Michigan > Chapter-125 > Act-57-of-1998 > Section-125-1592

CONTRACTS FOR IMPROVMENT TO REAL PROPERTY (EXCERPT)
Act 57 of 1998

125.1592 Improvement contract exceeding $75,000; provisions.

Sec. 2.

A contract between a contractor and a governmental entity for an improvement that exceeds $75,000.00 shall contain all of the following provisions:

(a) That if a contractor discovers 1 or both of the following physical conditions of the surface or subsurface at the improvement site, before disturbing the physical condition, the contractor shall promptly notify the governmental entity of the physical condition in writing:

(i) A subsurface or a latent physical condition at the site is differing materially from those indicated in the improvement contract.

(ii) An unknown physical condition at the site is of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the improvement contract.

(b) That if the governmental entity receives a notice under subdivision (a), the governmental entity shall promptly investigate the physical condition.

(c) That if the governmental entity determines that the physical conditions do materially differ and will cause an increase or decrease in costs or additional time needed to perform the contract, the governmental entity's determination shall be made in writing and an equitable adjustment shall be made and the contract modified in writing accordingly.

(d) That the contractor cannot make a claim for additional costs or time because of a physical condition unless the contractor has complied with the notice requirements of subdivision (a). The governmental entity may extend the time required for notice under subdivision (a).

(e) That the contractor cannot make a claim for an adjustment under the contract after the contractor has received the final payment under the contract.


History: 1998, Act 57, Eff. Oct. 6, 1998


State Codes and Statutes

State Codes and Statutes

Statutes > Michigan > Chapter-125 > Act-57-of-1998 > Section-125-1592

CONTRACTS FOR IMPROVMENT TO REAL PROPERTY (EXCERPT)
Act 57 of 1998

125.1592 Improvement contract exceeding $75,000; provisions.

Sec. 2.

A contract between a contractor and a governmental entity for an improvement that exceeds $75,000.00 shall contain all of the following provisions:

(a) That if a contractor discovers 1 or both of the following physical conditions of the surface or subsurface at the improvement site, before disturbing the physical condition, the contractor shall promptly notify the governmental entity of the physical condition in writing:

(i) A subsurface or a latent physical condition at the site is differing materially from those indicated in the improvement contract.

(ii) An unknown physical condition at the site is of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the improvement contract.

(b) That if the governmental entity receives a notice under subdivision (a), the governmental entity shall promptly investigate the physical condition.

(c) That if the governmental entity determines that the physical conditions do materially differ and will cause an increase or decrease in costs or additional time needed to perform the contract, the governmental entity's determination shall be made in writing and an equitable adjustment shall be made and the contract modified in writing accordingly.

(d) That the contractor cannot make a claim for additional costs or time because of a physical condition unless the contractor has complied with the notice requirements of subdivision (a). The governmental entity may extend the time required for notice under subdivision (a).

(e) That the contractor cannot make a claim for an adjustment under the contract after the contractor has received the final payment under the contract.


History: 1998, Act 57, Eff. Oct. 6, 1998