1395.  Actual construction work upon any project shall begin within
the time specified in the permit, which time shall not be less than
60 days from the date of the permit.



1396.  The construction of the work thereafter and the utilization
of water for beneficial purposes shall be prosecuted with due
diligence in accordance with this division, the terms of the permit,
and the rules and regulations of the board.




1397.  The work shall be completed and the water applied to
beneficial use in accordance with this division, the rules and
regulations of the board, and the terms of the permit and within the
period specified in the permit.


1398.  (a) The period specified in the permit for beginning
construction work, for completion of construction work, for
application of the water to beneficial use, or any or all of these
periods may, for good cause shown, be extended by the board.
   (b) After any hearing on a petition to extend the period or
periods, the board may revoke the permit in accordance with Section
1410.

State Codes and Statutes

Statutes > California > Wat > 1395-1398

WATER CODE
SECTION 1395-1398



1395.  Actual construction work upon any project shall begin within
the time specified in the permit, which time shall not be less than
60 days from the date of the permit.



1396.  The construction of the work thereafter and the utilization
of water for beneficial purposes shall be prosecuted with due
diligence in accordance with this division, the terms of the permit,
and the rules and regulations of the board.




1397.  The work shall be completed and the water applied to
beneficial use in accordance with this division, the rules and
regulations of the board, and the terms of the permit and within the
period specified in the permit.


1398.  (a) The period specified in the permit for beginning
construction work, for completion of construction work, for
application of the water to beneficial use, or any or all of these
periods may, for good cause shown, be extended by the board.
   (b) After any hearing on a petition to extend the period or
periods, the board may revoke the permit in accordance with Section
1410.


State Codes and Statutes

State Codes and Statutes

Statutes > California > Wat > 1395-1398

WATER CODE
SECTION 1395-1398



1395.  Actual construction work upon any project shall begin within
the time specified in the permit, which time shall not be less than
60 days from the date of the permit.



1396.  The construction of the work thereafter and the utilization
of water for beneficial purposes shall be prosecuted with due
diligence in accordance with this division, the terms of the permit,
and the rules and regulations of the board.




1397.  The work shall be completed and the water applied to
beneficial use in accordance with this division, the rules and
regulations of the board, and the terms of the permit and within the
period specified in the permit.


1398.  (a) The period specified in the permit for beginning
construction work, for completion of construction work, for
application of the water to beneficial use, or any or all of these
periods may, for good cause shown, be extended by the board.
   (b) After any hearing on a petition to extend the period or
periods, the board may revoke the permit in accordance with Section
1410.