12-631r.Storm sewers; construction of improvements
outside boundaries of municipality.
(a) Whenever the governing body of
any city
determines
it is necessary to construct storm sewers, channels,
retention basins or drains for the
purpose of
managing the storm drainage areas of all or any portion of
such city and in the
unincorporated areas outside of but within three miles of the corporate limits
of such city, the governing body may authorize the construction of such
storm sewers, channels, retention basins
or drains. Such construction
shall be authorized by ordinance. Such ordinance shall designate
where
such storm sewers, channels, retention basins or drains shall
be located. Construction of such
improvements located outside the corporate limits of a city shall not commence
unless such construction is approved by a resolution adopted by the board of
county commissioners of the county in which such improvements are to be
located.
(b) Whenever the governing body of any city determines it is necessary to
construct
storm sewers, retention basins, channels or drains for the purpose of managing
the storm drainage areas of all or any portion of which are located within
another city, the governing body may authorize construction of such storm
sewers, retention basins, channels or drains. Such construction shall be
authorized by ordinance. Such ordinance shall designate where such storm
sewers, retention basins, channels or drains shall be located. Construction of
improvements located within the corporate limits of another city shall not
commence unless such construction is approved by a resolution adopted by the
governing body of the city in which such improvements are to be located.
(c) Whenever the board of county commissioners of any county determines it
is
necessary to construct storm sewers, retention basins, channels or drains for
the purpose of managing the storm drainage areas of all or any portion of such
county, the board may authorize construction of such storm sewers, retention
basins, channels or drains. Such construction shall be authorized by
resolution. Such resolution shall designate where such storm sewers, retention
basins, channels or drains shall be located. Construction of improvements
located within the corporate limits of a city shall not commence unless such
construction is approved by a resolution adopted by the governing body of the
city in which such improvements are to be located.
History: L. 1911, ch. 103, § 1; L. 1915, ch. 146, § 1; L. 1917, ch. 106, § 1;
R.S. 1923, § 14-522; L. 1975, ch. 91, § 2;
L. 1999, ch. 13, § 1; July 1.
12-631r.Storm sewers; construction of improvements
outside boundaries of municipality.
(a) Whenever the governing body of
any city
determines
it is necessary to construct storm sewers, channels,
retention basins or drains for the
purpose of
managing the storm drainage areas of all or any portion of
such city and in the
unincorporated areas outside of but within three miles of the corporate limits
of such city, the governing body may authorize the construction of such
storm sewers, channels, retention basins
or drains. Such construction
shall be authorized by ordinance. Such ordinance shall designate
where
such storm sewers, channels, retention basins or drains shall
be located. Construction of such
improvements located outside the corporate limits of a city shall not commence
unless such construction is approved by a resolution adopted by the board of
county commissioners of the county in which such improvements are to be
located.
(b) Whenever the governing body of any city determines it is necessary to
construct
storm sewers, retention basins, channels or drains for the purpose of managing
the storm drainage areas of all or any portion of which are located within
another city, the governing body may authorize construction of such storm
sewers, retention basins, channels or drains. Such construction shall be
authorized by ordinance. Such ordinance shall designate where such storm
sewers, retention basins, channels or drains shall be located. Construction of
improvements located within the corporate limits of another city shall not
commence unless such construction is approved by a resolution adopted by the
governing body of the city in which such improvements are to be located.
(c) Whenever the board of county commissioners of any county determines it
is
necessary to construct storm sewers, retention basins, channels or drains for
the purpose of managing the storm drainage areas of all or any portion of such
county, the board may authorize construction of such storm sewers, retention
basins, channels or drains. Such construction shall be authorized by
resolution. Such resolution shall designate where such storm sewers, retention
basins, channels or drains shall be located. Construction of improvements
located within the corporate limits of a city shall not commence unless such
construction is approved by a resolution adopted by the governing body of the
city in which such improvements are to be located.
History: L. 1911, ch. 103, § 1; L. 1915, ch. 146, § 1; L. 1917, ch. 106, § 1;
R.S. 1923, § 14-522; L. 1975, ch. 91, § 2;
L. 1999, ch. 13, § 1; July 1.
12-631r.Storm sewers; construction of improvements
outside boundaries of municipality.
(a) Whenever the governing body of
any city
determines
it is necessary to construct storm sewers, channels,
retention basins or drains for the
purpose of
managing the storm drainage areas of all or any portion of
such city and in the
unincorporated areas outside of but within three miles of the corporate limits
of such city, the governing body may authorize the construction of such
storm sewers, channels, retention basins
or drains. Such construction
shall be authorized by ordinance. Such ordinance shall designate
where
such storm sewers, channels, retention basins or drains shall
be located. Construction of such
improvements located outside the corporate limits of a city shall not commence
unless such construction is approved by a resolution adopted by the board of
county commissioners of the county in which such improvements are to be
located.
(b) Whenever the governing body of any city determines it is necessary to
construct
storm sewers, retention basins, channels or drains for the purpose of managing
the storm drainage areas of all or any portion of which are located within
another city, the governing body may authorize construction of such storm
sewers, retention basins, channels or drains. Such construction shall be
authorized by ordinance. Such ordinance shall designate where such storm
sewers, retention basins, channels or drains shall be located. Construction of
improvements located within the corporate limits of another city shall not
commence unless such construction is approved by a resolution adopted by the
governing body of the city in which such improvements are to be located.
(c) Whenever the board of county commissioners of any county determines it
is
necessary to construct storm sewers, retention basins, channels or drains for
the purpose of managing the storm drainage areas of all or any portion of such
county, the board may authorize construction of such storm sewers, retention
basins, channels or drains. Such construction shall be authorized by
resolution. Such resolution shall designate where such storm sewers, retention
basins, channels or drains shall be located. Construction of improvements
located within the corporate limits of a city shall not commence unless such
construction is approved by a resolution adopted by the governing body of the
city in which such improvements are to be located.
History: L. 1911, ch. 103, § 1; L. 1915, ch. 146, § 1; L. 1917, ch. 106, § 1;
R.S. 1923, § 14-522; L. 1975, ch. 91, § 2;
L. 1999, ch. 13, § 1; July 1.