460.708 Information as to approximate location of underground facilities; color coding; additional assistance; removal or protection of facilities.

Sec. 8.

Not less than 1 working day in advance of proposed construction, unless otherwise agreed between the person or public agency performing the excavation, discharging of explosives, drilling, boring, tunneling, or demolition and the public utility, a public utility served with notice pursuant to section 5 or 7 shall inform the person or public agency of the approximate location of the underground facilities owned or operated by the public utility in the proposed area of excavation, discharging of explosives, drilling, boring, tunneling, or demolition, in a manner that enables the person or public agency to employ hand dug test holes or other similar means of establishing the precise location of the underground facilities using reasonable care to establish the precise location of the underground facilities in advance of construction. For the purposes of this act, the approximate location of underground facilities is defined as a strip of land at least 36 inches wide but not wider than the width of the facility plus 18 inches on either side of the facility. If the approximate location of an underground facility is marked with stakes or other physical means, the public utility shall follow the color coding prescribed in this section.

Utility and Type of Product Specific Group Identifying Color Electric power distribution and transmission Safety red Municipal electric systems Safety red Gas distribution and transmission High visibility safety yellow Oil distribution and transmission High visibility safety yellow Dangerous materials, product lines High visibility safety yellow Telephone and telegraph systems Safety alert orange Cable television Safety alert orange Police and fire communications Safety alert orange Water systems Safety precaution blue Sewer systems Safety brown Storm drains Safety green Land survey monumentation High visibility safety pink

All safety alert orange markings shall include the name or type of the company who owns the underground facility to be marked. If the precise location of the underground facilities cannot be established, the person or public agency shall then notify the public utility, which shall no later than 1 working day after the notice provide such further assistance as may be needed to determine the precise location of the underground facilities in advance of the proposed excavating, tunneling, discharging of explosives, drilling or boring procedures, or demolition operations. Where demolition of a building is proposed and the public utility is notified, it shall be given reasonable time to remove or protect its facilities before demolition of the building.


History: 1974, Act 53, Eff. Apr. 1, 1975 ;-- Am. 1975, Act 204, Imd. Eff. Aug. 20, 1975 ;-- Am. 1989, Act 248, Imd. Eff. Dec. 21, 1989 ;-- Am. 1994, Act 115, Imd. Eff. May 11, 1994

State Codes and Statutes

Statutes > Michigan > Chapter-460 > Act-53-of-1974 > Section-460-708

PROTECTION OF UNDERGROUND FACILITIES (EXCERPT)
Act 53 of 1974

460.708 Information as to approximate location of underground facilities; color coding; additional assistance; removal or protection of facilities.

Sec. 8.

Not less than 1 working day in advance of proposed construction, unless otherwise agreed between the person or public agency performing the excavation, discharging of explosives, drilling, boring, tunneling, or demolition and the public utility, a public utility served with notice pursuant to section 5 or 7 shall inform the person or public agency of the approximate location of the underground facilities owned or operated by the public utility in the proposed area of excavation, discharging of explosives, drilling, boring, tunneling, or demolition, in a manner that enables the person or public agency to employ hand dug test holes or other similar means of establishing the precise location of the underground facilities using reasonable care to establish the precise location of the underground facilities in advance of construction. For the purposes of this act, the approximate location of underground facilities is defined as a strip of land at least 36 inches wide but not wider than the width of the facility plus 18 inches on either side of the facility. If the approximate location of an underground facility is marked with stakes or other physical means, the public utility shall follow the color coding prescribed in this section.

Utility and Type of Product Specific Group Identifying Color Electric power distribution and transmission Safety red Municipal electric systems Safety red Gas distribution and transmission High visibility safety yellow Oil distribution and transmission High visibility safety yellow Dangerous materials, product lines High visibility safety yellow Telephone and telegraph systems Safety alert orange Cable television Safety alert orange Police and fire communications Safety alert orange Water systems Safety precaution blue Sewer systems Safety brown Storm drains Safety green Land survey monumentation High visibility safety pink

All safety alert orange markings shall include the name or type of the company who owns the underground facility to be marked. If the precise location of the underground facilities cannot be established, the person or public agency shall then notify the public utility, which shall no later than 1 working day after the notice provide such further assistance as may be needed to determine the precise location of the underground facilities in advance of the proposed excavating, tunneling, discharging of explosives, drilling or boring procedures, or demolition operations. Where demolition of a building is proposed and the public utility is notified, it shall be given reasonable time to remove or protect its facilities before demolition of the building.


History: 1974, Act 53, Eff. Apr. 1, 1975 ;-- Am. 1975, Act 204, Imd. Eff. Aug. 20, 1975 ;-- Am. 1989, Act 248, Imd. Eff. Dec. 21, 1989 ;-- Am. 1994, Act 115, Imd. Eff. May 11, 1994


State Codes and Statutes

State Codes and Statutes

Statutes > Michigan > Chapter-460 > Act-53-of-1974 > Section-460-708

PROTECTION OF UNDERGROUND FACILITIES (EXCERPT)
Act 53 of 1974

460.708 Information as to approximate location of underground facilities; color coding; additional assistance; removal or protection of facilities.

Sec. 8.

Not less than 1 working day in advance of proposed construction, unless otherwise agreed between the person or public agency performing the excavation, discharging of explosives, drilling, boring, tunneling, or demolition and the public utility, a public utility served with notice pursuant to section 5 or 7 shall inform the person or public agency of the approximate location of the underground facilities owned or operated by the public utility in the proposed area of excavation, discharging of explosives, drilling, boring, tunneling, or demolition, in a manner that enables the person or public agency to employ hand dug test holes or other similar means of establishing the precise location of the underground facilities using reasonable care to establish the precise location of the underground facilities in advance of construction. For the purposes of this act, the approximate location of underground facilities is defined as a strip of land at least 36 inches wide but not wider than the width of the facility plus 18 inches on either side of the facility. If the approximate location of an underground facility is marked with stakes or other physical means, the public utility shall follow the color coding prescribed in this section.

Utility and Type of Product Specific Group Identifying Color Electric power distribution and transmission Safety red Municipal electric systems Safety red Gas distribution and transmission High visibility safety yellow Oil distribution and transmission High visibility safety yellow Dangerous materials, product lines High visibility safety yellow Telephone and telegraph systems Safety alert orange Cable television Safety alert orange Police and fire communications Safety alert orange Water systems Safety precaution blue Sewer systems Safety brown Storm drains Safety green Land survey monumentation High visibility safety pink

All safety alert orange markings shall include the name or type of the company who owns the underground facility to be marked. If the precise location of the underground facilities cannot be established, the person or public agency shall then notify the public utility, which shall no later than 1 working day after the notice provide such further assistance as may be needed to determine the precise location of the underground facilities in advance of the proposed excavating, tunneling, discharging of explosives, drilling or boring procedures, or demolition operations. Where demolition of a building is proposed and the public utility is notified, it shall be given reasonable time to remove or protect its facilities before demolition of the building.


History: 1974, Act 53, Eff. Apr. 1, 1975 ;-- Am. 1975, Act 204, Imd. Eff. Aug. 20, 1975 ;-- Am. 1989, Act 248, Imd. Eff. Dec. 21, 1989 ;-- Am. 1994, Act 115, Imd. Eff. May 11, 1994