4929.05 Rrequesting approval of alternative rate plan.

(A) As part of an application filed pursuant to section 4909.18 of the Revised Code, a natural gas company may request approval of an alternative rate plan. After notice, investigation, and hearing, and after determining just and reasonable rates and charges for the natural gas company pursuant to section 4909.15 of the Revised Code, the public utilities commission shall authorize the applicant to implement an alternative rate plan if the natural gas company has made a showing and the commission finds that both of the following conditions are met:

(1) The natural gas company is in compliance with section 4905.35 of the Revised Code and is in substantial compliance with the policy of this state specified in section 4929.02 of the Revised Code;

(2) The natural gas company is expected to continue to be in substantial compliance with the policy of this state specified in section 4929.02 of the Revised Code after implementation of the alternative rate plan.

(B) The applicant shall have the burden of proof under this section.

(C) No request may be made under this section prior to one hundred eighty days after the effective date of this section.

Effective Date: 09-17-1996

State Codes and Statutes

Statutes > Ohio > Title49 > Chapter4929 > 4929_05

4929.05 Rrequesting approval of alternative rate plan.

(A) As part of an application filed pursuant to section 4909.18 of the Revised Code, a natural gas company may request approval of an alternative rate plan. After notice, investigation, and hearing, and after determining just and reasonable rates and charges for the natural gas company pursuant to section 4909.15 of the Revised Code, the public utilities commission shall authorize the applicant to implement an alternative rate plan if the natural gas company has made a showing and the commission finds that both of the following conditions are met:

(1) The natural gas company is in compliance with section 4905.35 of the Revised Code and is in substantial compliance with the policy of this state specified in section 4929.02 of the Revised Code;

(2) The natural gas company is expected to continue to be in substantial compliance with the policy of this state specified in section 4929.02 of the Revised Code after implementation of the alternative rate plan.

(B) The applicant shall have the burden of proof under this section.

(C) No request may be made under this section prior to one hundred eighty days after the effective date of this section.

Effective Date: 09-17-1996


State Codes and Statutes

State Codes and Statutes

Statutes > Ohio > Title49 > Chapter4929 > 4929_05

4929.05 Rrequesting approval of alternative rate plan.

(A) As part of an application filed pursuant to section 4909.18 of the Revised Code, a natural gas company may request approval of an alternative rate plan. After notice, investigation, and hearing, and after determining just and reasonable rates and charges for the natural gas company pursuant to section 4909.15 of the Revised Code, the public utilities commission shall authorize the applicant to implement an alternative rate plan if the natural gas company has made a showing and the commission finds that both of the following conditions are met:

(1) The natural gas company is in compliance with section 4905.35 of the Revised Code and is in substantial compliance with the policy of this state specified in section 4929.02 of the Revised Code;

(2) The natural gas company is expected to continue to be in substantial compliance with the policy of this state specified in section 4929.02 of the Revised Code after implementation of the alternative rate plan.

(B) The applicant shall have the burden of proof under this section.

(C) No request may be made under this section prior to one hundred eighty days after the effective date of this section.

Effective Date: 09-17-1996