State Codes and Statutes

Statutes > Ohio > Title55 > Chapter5575 > 5575_05

5575.05 New contract for extra work - procedure.

(A) In case of an unforeseen contingency not contemplated by a road improvement contract, allowances for extra work may be made by a board of township trustees, but the board must first enter into a new contract in writing for the extra work. If the estimate for extra work is less than twenty-five thousand dollars for any particular line item listed in the new contract and the overall total estimate for the extra work does not exceed ten per cent of the total of the original contract, the contract for the extra work may be let by the board by private contract without complying with section 5575.02 of the Revised Code. Section 5575.02 of the Revised Code applies to all other new contracts for extra work, except that if an emergency exists and the time required for complying with section 5575.02 of the Revised Code would unduly delay the completion of the project, the board, after making a finding of emergency and entering it on its records, may contract for the extra work by private contract without complying with that section.

(B) No contract shall be awarded for extra work at any price in excess of the original contract unit price for the same class or kind of work in connection with the original contract. In case of any new class or kind of work, the board and contractor shall agree as to the price to be paid. The contractor shall submit a bid in writing and, if the bid is accepted by the board, the board immediately shall enter into a written contract covering the extra work. The costs of the extra work shall be paid by the board out of any funds available therefor, and the amount paid shall be charged to the cost of construction of the improvement and apportioned as the original contract price.

Effective Date: 09-14-1995

State Codes and Statutes

Statutes > Ohio > Title55 > Chapter5575 > 5575_05

5575.05 New contract for extra work - procedure.

(A) In case of an unforeseen contingency not contemplated by a road improvement contract, allowances for extra work may be made by a board of township trustees, but the board must first enter into a new contract in writing for the extra work. If the estimate for extra work is less than twenty-five thousand dollars for any particular line item listed in the new contract and the overall total estimate for the extra work does not exceed ten per cent of the total of the original contract, the contract for the extra work may be let by the board by private contract without complying with section 5575.02 of the Revised Code. Section 5575.02 of the Revised Code applies to all other new contracts for extra work, except that if an emergency exists and the time required for complying with section 5575.02 of the Revised Code would unduly delay the completion of the project, the board, after making a finding of emergency and entering it on its records, may contract for the extra work by private contract without complying with that section.

(B) No contract shall be awarded for extra work at any price in excess of the original contract unit price for the same class or kind of work in connection with the original contract. In case of any new class or kind of work, the board and contractor shall agree as to the price to be paid. The contractor shall submit a bid in writing and, if the bid is accepted by the board, the board immediately shall enter into a written contract covering the extra work. The costs of the extra work shall be paid by the board out of any funds available therefor, and the amount paid shall be charged to the cost of construction of the improvement and apportioned as the original contract price.

Effective Date: 09-14-1995


State Codes and Statutes

State Codes and Statutes

Statutes > Ohio > Title55 > Chapter5575 > 5575_05

5575.05 New contract for extra work - procedure.

(A) In case of an unforeseen contingency not contemplated by a road improvement contract, allowances for extra work may be made by a board of township trustees, but the board must first enter into a new contract in writing for the extra work. If the estimate for extra work is less than twenty-five thousand dollars for any particular line item listed in the new contract and the overall total estimate for the extra work does not exceed ten per cent of the total of the original contract, the contract for the extra work may be let by the board by private contract without complying with section 5575.02 of the Revised Code. Section 5575.02 of the Revised Code applies to all other new contracts for extra work, except that if an emergency exists and the time required for complying with section 5575.02 of the Revised Code would unduly delay the completion of the project, the board, after making a finding of emergency and entering it on its records, may contract for the extra work by private contract without complying with that section.

(B) No contract shall be awarded for extra work at any price in excess of the original contract unit price for the same class or kind of work in connection with the original contract. In case of any new class or kind of work, the board and contractor shall agree as to the price to be paid. The contractor shall submit a bid in writing and, if the bid is accepted by the board, the board immediately shall enter into a written contract covering the extra work. The costs of the extra work shall be paid by the board out of any funds available therefor, and the amount paid shall be charged to the cost of construction of the improvement and apportioned as the original contract price.

Effective Date: 09-14-1995