State Codes and Statutes

Statutes > South-dakota > Title-34a > Chapter-01 > Statute-34a-1-32

34A-1-32. Limitation when variance based on time required for abatement measures. If the variance is granted on the ground that compliance with the particular requirement or requirements from which variance is sought will necessitate the taking of measures which, because of their extent or cost, must be spread over a considerable period of time, it shall be for a period not to exceed such reasonable time as, in the view of the board is requisite for the taking of the necessary measures. A variance granted on the ground specified herein shall contain a timetable for the taking of action in an expeditious manner and shall be conditioned on adherence to such timetable.

Source: SL 1970, ch 203, § 12; SDCL Supp, § 34-16A-37.

State Codes and Statutes

Statutes > South-dakota > Title-34a > Chapter-01 > Statute-34a-1-32

34A-1-32. Limitation when variance based on time required for abatement measures. If the variance is granted on the ground that compliance with the particular requirement or requirements from which variance is sought will necessitate the taking of measures which, because of their extent or cost, must be spread over a considerable period of time, it shall be for a period not to exceed such reasonable time as, in the view of the board is requisite for the taking of the necessary measures. A variance granted on the ground specified herein shall contain a timetable for the taking of action in an expeditious manner and shall be conditioned on adherence to such timetable.

Source: SL 1970, ch 203, § 12; SDCL Supp, § 34-16A-37.


State Codes and Statutes

State Codes and Statutes

Statutes > South-dakota > Title-34a > Chapter-01 > Statute-34a-1-32

34A-1-32. Limitation when variance based on time required for abatement measures. If the variance is granted on the ground that compliance with the particular requirement or requirements from which variance is sought will necessitate the taking of measures which, because of their extent or cost, must be spread over a considerable period of time, it shall be for a period not to exceed such reasonable time as, in the view of the board is requisite for the taking of the necessary measures. A variance granted on the ground specified herein shall contain a timetable for the taking of action in an expeditious manner and shall be conditioned on adherence to such timetable.

Source: SL 1970, ch 203, § 12; SDCL Supp, § 34-16A-37.