49-41B-15. Procedure followed by commission following receipt of application for permit. Within thirty days following receipt of an application for a permit, the commission shall:
(1) Schedule a public hearing;
(2) Notify the applicant of the hearing;
(3) Serve notice of the application and hearing upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility;
(4) Publish a notice of the time, place, and purpose of the public hearing in at least one newspaper of general circulation in counties totally or partially within the area of the proposed facility; and
(5) File a copy of the application with the auditor of the county or counties in which the proposed facility will be constructed.

Source: SL 1977, ch 390, § 9; SL 2006, ch 242, § 4; SL 2008, ch 246, § 2.

State Codes and Statutes

Statutes > South-dakota > Title-49 > Chapter-41b > Statute-49-41b-15

49-41B-15. Procedure followed by commission following receipt of application for permit. Within thirty days following receipt of an application for a permit, the commission shall:
(1) Schedule a public hearing;
(2) Notify the applicant of the hearing;
(3) Serve notice of the application and hearing upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility;
(4) Publish a notice of the time, place, and purpose of the public hearing in at least one newspaper of general circulation in counties totally or partially within the area of the proposed facility; and
(5) File a copy of the application with the auditor of the county or counties in which the proposed facility will be constructed.

Source: SL 1977, ch 390, § 9; SL 2006, ch 242, § 4; SL 2008, ch 246, § 2.


State Codes and Statutes

State Codes and Statutes

Statutes > South-dakota > Title-49 > Chapter-41b > Statute-49-41b-15

49-41B-15. Procedure followed by commission following receipt of application for permit. Within thirty days following receipt of an application for a permit, the commission shall:
(1) Schedule a public hearing;
(2) Notify the applicant of the hearing;
(3) Serve notice of the application and hearing upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility;
(4) Publish a notice of the time, place, and purpose of the public hearing in at least one newspaper of general circulation in counties totally or partially within the area of the proposed facility; and
(5) File a copy of the application with the auditor of the county or counties in which the proposed facility will be constructed.

Source: SL 1977, ch 390, § 9; SL 2006, ch 242, § 4; SL 2008, ch 246, § 2.