State Codes and Statutes

Statutes > Utah > Title-73 > Chapter-03b > 73-3b-202

73-3b-202. Issuance of recharge permit -- Criteria -- Conditions.
The state engineer:
(1) shall issue a recharge permit if:
(a) the applicant has:
(i) the technical and financial capability to construct and operate the recharge project;and
(ii) (A) a valid water right for the use of the water proposed to be artificially recharged;or
(B) an agreement to use the water proposed to be artificially recharged with a person whohas a valid water right for the use of the water proposed to be artificially recharged; and
(b) the project:
(i) is hydrologically feasible;
(ii) will not cause unreasonable harm to land;
(iii) will not impair any existing water right within the area of hydrologic impact; and
(iv) will not adversely affect the water quality of the aquifer;
(2) shall condition any approval on acquiring the applicable water quality permits prior toconstruction and operation of the recharge project; and
(3) may attach to the permit any condition the state engineer determines is appropriate.

Amended by Chapter 107, 2010 General Session

State Codes and Statutes

Statutes > Utah > Title-73 > Chapter-03b > 73-3b-202

73-3b-202. Issuance of recharge permit -- Criteria -- Conditions.
The state engineer:
(1) shall issue a recharge permit if:
(a) the applicant has:
(i) the technical and financial capability to construct and operate the recharge project;and
(ii) (A) a valid water right for the use of the water proposed to be artificially recharged;or
(B) an agreement to use the water proposed to be artificially recharged with a person whohas a valid water right for the use of the water proposed to be artificially recharged; and
(b) the project:
(i) is hydrologically feasible;
(ii) will not cause unreasonable harm to land;
(iii) will not impair any existing water right within the area of hydrologic impact; and
(iv) will not adversely affect the water quality of the aquifer;
(2) shall condition any approval on acquiring the applicable water quality permits prior toconstruction and operation of the recharge project; and
(3) may attach to the permit any condition the state engineer determines is appropriate.

Amended by Chapter 107, 2010 General Session


State Codes and Statutes

State Codes and Statutes

Statutes > Utah > Title-73 > Chapter-03b > 73-3b-202

73-3b-202. Issuance of recharge permit -- Criteria -- Conditions.
The state engineer:
(1) shall issue a recharge permit if:
(a) the applicant has:
(i) the technical and financial capability to construct and operate the recharge project;and
(ii) (A) a valid water right for the use of the water proposed to be artificially recharged;or
(B) an agreement to use the water proposed to be artificially recharged with a person whohas a valid water right for the use of the water proposed to be artificially recharged; and
(b) the project:
(i) is hydrologically feasible;
(ii) will not cause unreasonable harm to land;
(iii) will not impair any existing water right within the area of hydrologic impact; and
(iv) will not adversely affect the water quality of the aquifer;
(2) shall condition any approval on acquiring the applicable water quality permits prior toconstruction and operation of the recharge project; and
(3) may attach to the permit any condition the state engineer determines is appropriate.

Amended by Chapter 107, 2010 General Session