Final orders.

(1) The board shall issue a final order that shall be based exclusively on whether or not a state agency, county, or city is in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW.

     (2)(a) Except as provided in (b) of this subsection, the final order shall be issued within one hundred eighty days of receipt of the petition for review, or, if multiple petitions are filed, within one hundred eighty days of receipt of the last petition that is consolidated.

     (b) The board may extend the period of time for issuing a decision to enable the parties to settle the dispute if additional time is necessary to achieve a settlement, and (i) an extension is requested by all parties, or (ii) an extension is requested by the petitioner and respondent and the board determines that a negotiated settlement between the remaining parties could resolve significant issues in dispute. The request must be filed with the board not later than seven days before the date scheduled for the hearing on the merits of the petition. The board may authorize one or more extensions for up to ninety days each, subject to the requirements of this section.

     (3) In the final order, the board shall either:

     (a) Find that the state agency, county, or city is in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW; or

     (b) Find that the state agency, county, or city is not in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW, in which case the board shall remand the matter to the affected state agency, county, or city. The board shall specify a reasonable time not in excess of one hundred eighty days, or such longer period as determined by the board in cases of unusual scope or complexity, within which the state agency, county, or city shall comply with the requirements of this chapter. The board may require periodic reports to the board on the progress the jurisdiction is making towards compliance.

     (4) Unless the board makes a determination of invalidity as provided in RCW 36.70A.302, a finding of noncompliance and an order of remand shall not affect the validity of comprehensive plans and development regulations during the period of remand.

     (5) Any party aggrieved by a final decision of the hearings board may appeal the decision to superior court as provided in RCW 34.05.514 or 36.01.050 within thirty days of the final order of the board.

[1997 c 429 § 14; 1995 c 347 § 110; 1991 sp.s. c 32 § 11.]

Notes: Prospective application -- 1997 c 429 §§ 1-21: See note following RCW 36.70A.3201.

Severability -- 1997 c 429: See note following RCW 36.70A.3201.

Finding -- Severability -- Part headings and table of contents not law -- 1995 c 347: See notes following RCW 36.70A.470.

State Codes and Statutes

Statutes > Washington > Title-36 > 36-70a > 36-70a-300

Final orders.

(1) The board shall issue a final order that shall be based exclusively on whether or not a state agency, county, or city is in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW.

     (2)(a) Except as provided in (b) of this subsection, the final order shall be issued within one hundred eighty days of receipt of the petition for review, or, if multiple petitions are filed, within one hundred eighty days of receipt of the last petition that is consolidated.

     (b) The board may extend the period of time for issuing a decision to enable the parties to settle the dispute if additional time is necessary to achieve a settlement, and (i) an extension is requested by all parties, or (ii) an extension is requested by the petitioner and respondent and the board determines that a negotiated settlement between the remaining parties could resolve significant issues in dispute. The request must be filed with the board not later than seven days before the date scheduled for the hearing on the merits of the petition. The board may authorize one or more extensions for up to ninety days each, subject to the requirements of this section.

     (3) In the final order, the board shall either:

     (a) Find that the state agency, county, or city is in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW; or

     (b) Find that the state agency, county, or city is not in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW, in which case the board shall remand the matter to the affected state agency, county, or city. The board shall specify a reasonable time not in excess of one hundred eighty days, or such longer period as determined by the board in cases of unusual scope or complexity, within which the state agency, county, or city shall comply with the requirements of this chapter. The board may require periodic reports to the board on the progress the jurisdiction is making towards compliance.

     (4) Unless the board makes a determination of invalidity as provided in RCW 36.70A.302, a finding of noncompliance and an order of remand shall not affect the validity of comprehensive plans and development regulations during the period of remand.

     (5) Any party aggrieved by a final decision of the hearings board may appeal the decision to superior court as provided in RCW 34.05.514 or 36.01.050 within thirty days of the final order of the board.

[1997 c 429 § 14; 1995 c 347 § 110; 1991 sp.s. c 32 § 11.]

Notes: Prospective application -- 1997 c 429 §§ 1-21: See note following RCW 36.70A.3201.

Severability -- 1997 c 429: See note following RCW 36.70A.3201.

Finding -- Severability -- Part headings and table of contents not law -- 1995 c 347: See notes following RCW 36.70A.470.


State Codes and Statutes

State Codes and Statutes

Statutes > Washington > Title-36 > 36-70a > 36-70a-300

Final orders.

(1) The board shall issue a final order that shall be based exclusively on whether or not a state agency, county, or city is in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW.

     (2)(a) Except as provided in (b) of this subsection, the final order shall be issued within one hundred eighty days of receipt of the petition for review, or, if multiple petitions are filed, within one hundred eighty days of receipt of the last petition that is consolidated.

     (b) The board may extend the period of time for issuing a decision to enable the parties to settle the dispute if additional time is necessary to achieve a settlement, and (i) an extension is requested by all parties, or (ii) an extension is requested by the petitioner and respondent and the board determines that a negotiated settlement between the remaining parties could resolve significant issues in dispute. The request must be filed with the board not later than seven days before the date scheduled for the hearing on the merits of the petition. The board may authorize one or more extensions for up to ninety days each, subject to the requirements of this section.

     (3) In the final order, the board shall either:

     (a) Find that the state agency, county, or city is in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW; or

     (b) Find that the state agency, county, or city is not in compliance with the requirements of this chapter, chapter 90.58 RCW as it relates to the adoption or amendment of shoreline master programs, or chapter 43.21C RCW as it relates to adoption of plans, development regulations, and amendments thereto, under RCW 36.70A.040 or chapter 90.58 RCW, in which case the board shall remand the matter to the affected state agency, county, or city. The board shall specify a reasonable time not in excess of one hundred eighty days, or such longer period as determined by the board in cases of unusual scope or complexity, within which the state agency, county, or city shall comply with the requirements of this chapter. The board may require periodic reports to the board on the progress the jurisdiction is making towards compliance.

     (4) Unless the board makes a determination of invalidity as provided in RCW 36.70A.302, a finding of noncompliance and an order of remand shall not affect the validity of comprehensive plans and development regulations during the period of remand.

     (5) Any party aggrieved by a final decision of the hearings board may appeal the decision to superior court as provided in RCW 34.05.514 or 36.01.050 within thirty days of the final order of the board.

[1997 c 429 § 14; 1995 c 347 § 110; 1991 sp.s. c 32 § 11.]

Notes: Prospective application -- 1997 c 429 §§ 1-21: See note following RCW 36.70A.3201.

Severability -- 1997 c 429: See note following RCW 36.70A.3201.

Finding -- Severability -- Part headings and table of contents not law -- 1995 c 347: See notes following RCW 36.70A.470.