§269-104 - Additional customer-generators.
§269-104 Additional customer-generators.
Notwithstanding section 269-102, an electric utility is not obligated to
provide net energy metering to additional customer-generators in its service
area when the combined total peak generating capacity of all eligible
customer-generators served by all the electric utilities in that service area
furnishing net energy metering to eligible customer-generators equals .5 per
cent of the system peak demand of those electric utilities; provided that the
public utilities commission may increase, by rule or order, the allowable
percentage of the electric utility's system peak demand produced from eligible
customer-generators in the electric utility's service area, whereupon the
electric utility will be obligated to provide net energy metering to additional
eligible customer-generators in that service area up to the increased
percentage amount. [L 2001, c 272, pt of §6; am L 2005, c 104, §4]