IC 5-30-2
    Chapter 2. General Provisions

IC 5-30-2-1
Validity of design-build contract
    
Sec. 1. A design-build contract awarded as provided in thischapter is valid and enforceable.
As added by P.L.74-2005, SEC.1.

IC 5-30-2-2
Adoption of resolution required
    
Sec. 2. Before entering into a design-build contract under thisarticle for a public project, the governing body of a public agencymust adopt a resolution authorizing the use of the design-buildcontracting method for the public project. The resolution mustidentify the members of the technical review committee appointedunder IC 5-30-4. The governing body must adopt the resolution at apublic meeting for which public notice has been provided.
As added by P.L.74-2005, SEC.1.