338.169  Public body authorized to construct public work by selecting and entering into contracts with construction manager at risk. [Effective July 1, 2011.]  A public body may construct a public work by:

1.  Selecting a construction manager at risk pursuant to the provisions of NRS 338.1691 to 338.1696, inclusive; and

2.  Entering into separate contracts with a construction manager at risk:

(a) For preconstruction services, including, without limitation:

(1) Assisting the public body in determining whether scheduling or design problems exist that would delay the construction of the public work;

(2) Estimating the cost of the labor and material for the public work; and

(3) Assisting the public body in determining whether the public work can be constructed within the public body’s budget; and

(b) To construct the public work.

(Added to NRS by 2007, 2891; A 2009, 437, effective July 1, 2011)