341.145  Powers and duties of Board: Design, construction and repairs.  The Board:

      1.  Shall determine whether any rebates are available from a public utility for installing devices in any state building which are designed to decrease the use of energy in the building. If such a rebate is available, the Board shall apply for the rebate.

      2.  Shall solicit bids for and let all contracts for new construction or major repairs.

      3.  May negotiate with the lowest responsible and responsive bidder on any contract to obtain a revised bid if:

      (a) The bid is less than the appropriation made by the Legislature for that building project; and

      (b) The bid does not exceed the relevant budget item for that building project as established by the Board by more than 10 percent.

      4.  May reject any or all bids.

      5.  After the contract is let, shall supervise and inspect construction and major repairs. The cost of supervision and inspection must be financed from the capital construction program approved by the Legislature.

      6.  Shall obtain prior approval from the Interim Finance Committee before authorizing any change in the scope of the design or construction of a project as that project was authorized by the Legislature, if the change increases or decreases the total square footage or cost of the project by 10 percent or more.

      7.  Except for changes that require prior approval pursuant to subsection 6, may authorize change orders, before or during construction:

      (a) In any amount, where the change represents a reduction in the total awarded contract price.

      (b) Except as otherwise provided in paragraph (c), not to exceed in the aggregate 15 percent of the total awarded contract price, where the change represents an increase in that price.

      (c) In any amount, where the total awarded contract price is less than $50,000 and the change represents an increase not exceeding the amount of the total awarded contract price.

      (d) In any amount, where additional money was authorized or appropriated by the Legislature and issuing a new contract would not be in the best interests of the State.

      8.  Shall specify in any contract with a design professional the period within which the design professional must prepare and submit to the Board a change order that has been authorized by the design professional. As used in this subsection, “design professional” means a person with a professional license or certificate issued pursuant to chapter 623, 623A or 625 of NRS.

      9.  Has final authority to accept each building or structure, or any portion thereof, on property of the State or held in trust for any division of the State Government as completed or to require necessary alterations to conform to the contract or to codes adopted by the Board, and to file the notice of completion and certificate of occupancy for the building or structure.

      (Added to NRS by 1985, 58; A 1995, 382; 2001, 1916; 2003, 2484; 2007, 3271)

     

State Codes and Statutes

Statutes > Nevada > Title-28 > Chapter-341 > 341-145

341.145  Powers and duties of Board: Design, construction and repairs.  The Board:

      1.  Shall determine whether any rebates are available from a public utility for installing devices in any state building which are designed to decrease the use of energy in the building. If such a rebate is available, the Board shall apply for the rebate.

      2.  Shall solicit bids for and let all contracts for new construction or major repairs.

      3.  May negotiate with the lowest responsible and responsive bidder on any contract to obtain a revised bid if:

      (a) The bid is less than the appropriation made by the Legislature for that building project; and

      (b) The bid does not exceed the relevant budget item for that building project as established by the Board by more than 10 percent.

      4.  May reject any or all bids.

      5.  After the contract is let, shall supervise and inspect construction and major repairs. The cost of supervision and inspection must be financed from the capital construction program approved by the Legislature.

      6.  Shall obtain prior approval from the Interim Finance Committee before authorizing any change in the scope of the design or construction of a project as that project was authorized by the Legislature, if the change increases or decreases the total square footage or cost of the project by 10 percent or more.

      7.  Except for changes that require prior approval pursuant to subsection 6, may authorize change orders, before or during construction:

      (a) In any amount, where the change represents a reduction in the total awarded contract price.

      (b) Except as otherwise provided in paragraph (c), not to exceed in the aggregate 15 percent of the total awarded contract price, where the change represents an increase in that price.

      (c) In any amount, where the total awarded contract price is less than $50,000 and the change represents an increase not exceeding the amount of the total awarded contract price.

      (d) In any amount, where additional money was authorized or appropriated by the Legislature and issuing a new contract would not be in the best interests of the State.

      8.  Shall specify in any contract with a design professional the period within which the design professional must prepare and submit to the Board a change order that has been authorized by the design professional. As used in this subsection, “design professional” means a person with a professional license or certificate issued pursuant to chapter 623, 623A or 625 of NRS.

      9.  Has final authority to accept each building or structure, or any portion thereof, on property of the State or held in trust for any division of the State Government as completed or to require necessary alterations to conform to the contract or to codes adopted by the Board, and to file the notice of completion and certificate of occupancy for the building or structure.

      (Added to NRS by 1985, 58; A 1995, 382; 2001, 1916; 2003, 2484; 2007, 3271)

     


State Codes and Statutes

State Codes and Statutes

Statutes > Nevada > Title-28 > Chapter-341 > 341-145

341.145  Powers and duties of Board: Design, construction and repairs.  The Board:

      1.  Shall determine whether any rebates are available from a public utility for installing devices in any state building which are designed to decrease the use of energy in the building. If such a rebate is available, the Board shall apply for the rebate.

      2.  Shall solicit bids for and let all contracts for new construction or major repairs.

      3.  May negotiate with the lowest responsible and responsive bidder on any contract to obtain a revised bid if:

      (a) The bid is less than the appropriation made by the Legislature for that building project; and

      (b) The bid does not exceed the relevant budget item for that building project as established by the Board by more than 10 percent.

      4.  May reject any or all bids.

      5.  After the contract is let, shall supervise and inspect construction and major repairs. The cost of supervision and inspection must be financed from the capital construction program approved by the Legislature.

      6.  Shall obtain prior approval from the Interim Finance Committee before authorizing any change in the scope of the design or construction of a project as that project was authorized by the Legislature, if the change increases or decreases the total square footage or cost of the project by 10 percent or more.

      7.  Except for changes that require prior approval pursuant to subsection 6, may authorize change orders, before or during construction:

      (a) In any amount, where the change represents a reduction in the total awarded contract price.

      (b) Except as otherwise provided in paragraph (c), not to exceed in the aggregate 15 percent of the total awarded contract price, where the change represents an increase in that price.

      (c) In any amount, where the total awarded contract price is less than $50,000 and the change represents an increase not exceeding the amount of the total awarded contract price.

      (d) In any amount, where additional money was authorized or appropriated by the Legislature and issuing a new contract would not be in the best interests of the State.

      8.  Shall specify in any contract with a design professional the period within which the design professional must prepare and submit to the Board a change order that has been authorized by the design professional. As used in this subsection, “design professional” means a person with a professional license or certificate issued pursuant to chapter 623, 623A or 625 of NRS.

      9.  Has final authority to accept each building or structure, or any portion thereof, on property of the State or held in trust for any division of the State Government as completed or to require necessary alterations to conform to the contract or to codes adopted by the Board, and to file the notice of completion and certificate of occupancy for the building or structure.

      (Added to NRS by 1985, 58; A 1995, 382; 2001, 1916; 2003, 2484; 2007, 3271)