519A.220 - Applicant to complete checklist for permit; contents.
1. Â Information relating to the plan for reclamation, including:
(a) The proposed subsequent use of the land after the mining operation is completed;
(b) The proposed schedule of reclamation that will be followed;
(c) The proposed topography of the land after the mining operation is completed;
(d) The treatment of slopes created or affected by the mining operation;
(e) The proposed use of impoundments;
(f) The kinds of access roads to be built and the manner of reclamation of road sites;
(g) The methods of drainage that will be used during the mining operation and reclamation;
(h) The revegetation of the land;
(i) The monitoring and maintenance of the reclaimed land that will be performed by the operator;
(j) The reclamation that will be necessary as a result of instream mining;
(k) The effect that reclamation will have on future mining in that area; and
(l) The effect of the reclamation on public safety.
2. Â Information relating to the mining operation and maps of the area which is required by the regulations adopted by the Commission pursuant to NRS 519A.160.
3. Â Other information as requested by the Administrator which the Administrator determines is pertinent to the reclamation activities of the mining operation.
(Added to NRS by 1989, 1285)