704.891  Reports to be filed with Commission by person holding permit who is not public utility.  

      1.  Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900, inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:

      (a) The location, nature and capacity of that facility;

      (b) The anticipated date for commercial operation of that facility;

      (c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and

      (d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.

      2.  The reports required by subsection 1 must be filed:

      (a) On or before the date on which construction of a utility facility is commenced; and

      (b) On a date not later than:

             (1) Twelve months before the scheduled date of commercial operation of that facility; or

             (2) Thirty days before the actual date of commercial operation of that facility,

Ê whichever is earlier.

      (Added to NRS by 1985, 2297; A 1997, 1917; 2001, 2989)

     

State Codes and Statutes

Statutes > Nevada > Title-58 > Chapter-704 > Construction-of-utility-facilities-utility-environmental-protection-act > 704-891

704.891  Reports to be filed with Commission by person holding permit who is not public utility.  

      1.  Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900, inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:

      (a) The location, nature and capacity of that facility;

      (b) The anticipated date for commercial operation of that facility;

      (c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and

      (d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.

      2.  The reports required by subsection 1 must be filed:

      (a) On or before the date on which construction of a utility facility is commenced; and

      (b) On a date not later than:

             (1) Twelve months before the scheduled date of commercial operation of that facility; or

             (2) Thirty days before the actual date of commercial operation of that facility,

Ê whichever is earlier.

      (Added to NRS by 1985, 2297; A 1997, 1917; 2001, 2989)

     


State Codes and Statutes

State Codes and Statutes

Statutes > Nevada > Title-58 > Chapter-704 > Construction-of-utility-facilities-utility-environmental-protection-act > 704-891

704.891  Reports to be filed with Commission by person holding permit who is not public utility.  

      1.  Any person other than a public utility who receives a permit issued by the Commission pursuant to NRS 704.820 to 704.900, inclusive, shall, as provided in subsection 2, file with the Commission reports which contain:

      (a) The location, nature and capacity of that facility;

      (b) The anticipated date for commercial operation of that facility;

      (c) Information regarding whether any public utility in this state has contracted for the purchase of the capacity or other services of that facility; and

      (d) Information regarding whether any capacity or other services of that facility is available for purchase by public utilities in this state.

      2.  The reports required by subsection 1 must be filed:

      (a) On or before the date on which construction of a utility facility is commenced; and

      (b) On a date not later than:

             (1) Twelve months before the scheduled date of commercial operation of that facility; or

             (2) Thirty days before the actual date of commercial operation of that facility,

Ê whichever is earlier.

      (Added to NRS by 1985, 2297; A 1997, 1917; 2001, 2989)