        208.28  FORFEITURE OF BOND -- LICENSURE
      RESTRICTIONS.
         1.  The attorney general, upon request of the division, shall
      institute proceedings for forfeiture of the bond posted by an
      operator to guarantee reclamation of a site where the operator is in
      violation of any of the provisions of this chapter or any rule
      adopted by the division pursuant to this chapter.  The division shall
      have the power to reclaim as required by section 208.17 any mined
      land with respect to which a bond has been forfeited, using the
      proceeds of the forfeiture to pay for the necessary reclamation work
      and associated administrative costs.
         2.  If the proceeds from bond forfeiture proceedings are
      insufficient to fully satisfy the estimated cost of reclaiming
      disturbed lands as required under section 208.17 and division rules,
      the operator shall be liable for remaining costs.  The division may
      complete, or authorize completion of, the necessary reclamation and
      may authorize the attorney general to bring a civil action to recover
      from the operator all actual or estimated costs of reclamation in
      excess of the amount forfeited or require the operator to complete
      reclamation.
         3.  If the amount of bond forfeited exceeds the amount necessary
      to complete reclamation, the unused funds shall be returned to the
      operator or the surety, as appropriate.  
         Section History: Early Form
         [C71, 73, 75, 77, 79, 81, § 83A.28] 
         Section History: Recent Form
         85 Acts, ch 137, §20
         C93, § 208.28
         96 Acts, ch 1043, §19

State Codes and Statutes

Statutes > Iowa > Title-5 > Subtitle-4 > Chapter-208 > 208-28

        208.28  FORFEITURE OF BOND -- LICENSURE
      RESTRICTIONS.
         1.  The attorney general, upon request of the division, shall
      institute proceedings for forfeiture of the bond posted by an
      operator to guarantee reclamation of a site where the operator is in
      violation of any of the provisions of this chapter or any rule
      adopted by the division pursuant to this chapter.  The division shall
      have the power to reclaim as required by section 208.17 any mined
      land with respect to which a bond has been forfeited, using the
      proceeds of the forfeiture to pay for the necessary reclamation work
      and associated administrative costs.
         2.  If the proceeds from bond forfeiture proceedings are
      insufficient to fully satisfy the estimated cost of reclaiming
      disturbed lands as required under section 208.17 and division rules,
      the operator shall be liable for remaining costs.  The division may
      complete, or authorize completion of, the necessary reclamation and
      may authorize the attorney general to bring a civil action to recover
      from the operator all actual or estimated costs of reclamation in
      excess of the amount forfeited or require the operator to complete
      reclamation.
         3.  If the amount of bond forfeited exceeds the amount necessary
      to complete reclamation, the unused funds shall be returned to the
      operator or the surety, as appropriate.  
         Section History: Early Form
         [C71, 73, 75, 77, 79, 81, § 83A.28] 
         Section History: Recent Form
         85 Acts, ch 137, §20
         C93, § 208.28
         96 Acts, ch 1043, §19

State Codes and Statutes

State Codes and Statutes

Statutes > Iowa > Title-5 > Subtitle-4 > Chapter-208 > 208-28

        208.28  FORFEITURE OF BOND -- LICENSURE
      RESTRICTIONS.
         1.  The attorney general, upon request of the division, shall
      institute proceedings for forfeiture of the bond posted by an
      operator to guarantee reclamation of a site where the operator is in
      violation of any of the provisions of this chapter or any rule
      adopted by the division pursuant to this chapter.  The division shall
      have the power to reclaim as required by section 208.17 any mined
      land with respect to which a bond has been forfeited, using the
      proceeds of the forfeiture to pay for the necessary reclamation work
      and associated administrative costs.
         2.  If the proceeds from bond forfeiture proceedings are
      insufficient to fully satisfy the estimated cost of reclaiming
      disturbed lands as required under section 208.17 and division rules,
      the operator shall be liable for remaining costs.  The division may
      complete, or authorize completion of, the necessary reclamation and
      may authorize the attorney general to bring a civil action to recover
      from the operator all actual or estimated costs of reclamation in
      excess of the amount forfeited or require the operator to complete
      reclamation.
         3.  If the amount of bond forfeited exceeds the amount necessary
      to complete reclamation, the unused funds shall be returned to the
      operator or the surety, as appropriate.  
         Section History: Early Form
         [C71, 73, 75, 77, 79, 81, § 83A.28] 
         Section History: Recent Form
         85 Acts, ch 137, §20
         C93, § 208.28
         96 Acts, ch 1043, §19