State Codes and Statutes

Statutes > Utah > Title-54 > Chapter-17 > 54-17-102

54-17-102. Definitions.
As used in this chapter:
(1) "Affected electrical utility" means an electrical corporation with at least 200,000retail customers in the state.
(2) "Benchmark option" means an energy resource against which bids in an open bidprocess may be evaluated that:
(a) could be constructed or owned by:
(i) an affected electrical utility; or
(ii) an affiliate of an affected electrical utility; or
(b) may be a purchase of:
(i) electricity;
(ii) electric generating capacity; or
(iii) electricity and electric generating capacity.
(3) "Integrated resource plan" means a plan that contains:
(a) the demand and energy forecast by the affected electrical utility for at least a ten-yearperiod;
(b) the affected electrical utility's options for meeting the requirements shown in its loadand resource forecast in an economic and reliable manner, including:
(i) demand-side and supply-side options; and
(ii) a brief description and summary cost-benefit analysis, if available, of each option thatwas considered;
(c) the affected electrical utility's assumptions and conclusions with respect to the effectof the plan on the cost and reliability of energy service;
(d) a description of the external environmental and economic consequences of the plan tothe extent practicable; and
(e) any other data and analyses as the commission may require.
(4) "Significant energy resource" for an affected electrical utility means a resource thatconsists of:
(a) a total of 100 megawatts or more of new generating capacity that has a dependablelife of 10 or more years;
(b) a purchase of the following if the contract is for a term of 10 or more years and notless than 100 megawatts:
(i) electricity;
(ii) electric generating capacity; or
(iii) electricity and electrical generating capacity;
(c) the purchase or lease by an affected electrical utility from an affiliated company of:
(i) a generating facility;
(ii) electricity;
(iii) electrical generating capacity; or
(iv) electricity and electrical generating capacity;
(d) a contract with an option for the affected electrical utility or an affiliate to purchase aresource that consists of not less than 100 megawatts or more of new generating capacity that hasa remaining dependable life of 10 or more years; or
(e) a type of resource designated by the commission as a significant energy resource inrules made by the commission in accordance with Title 63G, Chapter 3, Utah Administrative

Rulemaking Act, after considering the affected electrical utility's integrated resource plan andaction plan.
(5) "Solicitation" means a request for proposals or other invitation for persons to submita bid or proposal through an open bid process for construction or acquisition of a significantenergy resource.

Amended by Chapter 382, 2008 General Session

State Codes and Statutes

Statutes > Utah > Title-54 > Chapter-17 > 54-17-102

54-17-102. Definitions.
As used in this chapter:
(1) "Affected electrical utility" means an electrical corporation with at least 200,000retail customers in the state.
(2) "Benchmark option" means an energy resource against which bids in an open bidprocess may be evaluated that:
(a) could be constructed or owned by:
(i) an affected electrical utility; or
(ii) an affiliate of an affected electrical utility; or
(b) may be a purchase of:
(i) electricity;
(ii) electric generating capacity; or
(iii) electricity and electric generating capacity.
(3) "Integrated resource plan" means a plan that contains:
(a) the demand and energy forecast by the affected electrical utility for at least a ten-yearperiod;
(b) the affected electrical utility's options for meeting the requirements shown in its loadand resource forecast in an economic and reliable manner, including:
(i) demand-side and supply-side options; and
(ii) a brief description and summary cost-benefit analysis, if available, of each option thatwas considered;
(c) the affected electrical utility's assumptions and conclusions with respect to the effectof the plan on the cost and reliability of energy service;
(d) a description of the external environmental and economic consequences of the plan tothe extent practicable; and
(e) any other data and analyses as the commission may require.
(4) "Significant energy resource" for an affected electrical utility means a resource thatconsists of:
(a) a total of 100 megawatts or more of new generating capacity that has a dependablelife of 10 or more years;
(b) a purchase of the following if the contract is for a term of 10 or more years and notless than 100 megawatts:
(i) electricity;
(ii) electric generating capacity; or
(iii) electricity and electrical generating capacity;
(c) the purchase or lease by an affected electrical utility from an affiliated company of:
(i) a generating facility;
(ii) electricity;
(iii) electrical generating capacity; or
(iv) electricity and electrical generating capacity;
(d) a contract with an option for the affected electrical utility or an affiliate to purchase aresource that consists of not less than 100 megawatts or more of new generating capacity that hasa remaining dependable life of 10 or more years; or
(e) a type of resource designated by the commission as a significant energy resource inrules made by the commission in accordance with Title 63G, Chapter 3, Utah Administrative

Rulemaking Act, after considering the affected electrical utility's integrated resource plan andaction plan.
(5) "Solicitation" means a request for proposals or other invitation for persons to submita bid or proposal through an open bid process for construction or acquisition of a significantenergy resource.

Amended by Chapter 382, 2008 General Session


State Codes and Statutes

State Codes and Statutes

Statutes > Utah > Title-54 > Chapter-17 > 54-17-102

54-17-102. Definitions.
As used in this chapter:
(1) "Affected electrical utility" means an electrical corporation with at least 200,000retail customers in the state.
(2) "Benchmark option" means an energy resource against which bids in an open bidprocess may be evaluated that:
(a) could be constructed or owned by:
(i) an affected electrical utility; or
(ii) an affiliate of an affected electrical utility; or
(b) may be a purchase of:
(i) electricity;
(ii) electric generating capacity; or
(iii) electricity and electric generating capacity.
(3) "Integrated resource plan" means a plan that contains:
(a) the demand and energy forecast by the affected electrical utility for at least a ten-yearperiod;
(b) the affected electrical utility's options for meeting the requirements shown in its loadand resource forecast in an economic and reliable manner, including:
(i) demand-side and supply-side options; and
(ii) a brief description and summary cost-benefit analysis, if available, of each option thatwas considered;
(c) the affected electrical utility's assumptions and conclusions with respect to the effectof the plan on the cost and reliability of energy service;
(d) a description of the external environmental and economic consequences of the plan tothe extent practicable; and
(e) any other data and analyses as the commission may require.
(4) "Significant energy resource" for an affected electrical utility means a resource thatconsists of:
(a) a total of 100 megawatts or more of new generating capacity that has a dependablelife of 10 or more years;
(b) a purchase of the following if the contract is for a term of 10 or more years and notless than 100 megawatts:
(i) electricity;
(ii) electric generating capacity; or
(iii) electricity and electrical generating capacity;
(c) the purchase or lease by an affected electrical utility from an affiliated company of:
(i) a generating facility;
(ii) electricity;
(iii) electrical generating capacity; or
(iv) electricity and electrical generating capacity;
(d) a contract with an option for the affected electrical utility or an affiliate to purchase aresource that consists of not less than 100 megawatts or more of new generating capacity that hasa remaining dependable life of 10 or more years; or
(e) a type of resource designated by the commission as a significant energy resource inrules made by the commission in accordance with Title 63G, Chapter 3, Utah Administrative

Rulemaking Act, after considering the affected electrical utility's integrated resource plan andaction plan.
(5) "Solicitation" means a request for proposals or other invitation for persons to submita bid or proposal through an open bid process for construction or acquisition of a significantenergy resource.

Amended by Chapter 382, 2008 General Session