General contractor/construction manager procedure — Uses.

Subject to the process in RCW 39.10.270 or 39.10.280, public bodies may utilize the general contractor/construction manager procedure for public works projects where:

     (1) Implementation of the project involves complex scheduling, phasing, or coordination;

     (2) The project involves construction at an occupied facility which must continue to operate during construction;

     (3) The involvement of the general contractor/construction manager during the design stage is critical to the success of the project;

     (4) The project encompasses a complex or technical work environment; or

     (5) The project requires specialized work on a building that has historic significance.

[2007 c 494 § 301. Prior: 2003 c 352 § 3; 2003 c 300 § 5; 2002 c 46 § 2; 2001 c 328 § 3. Formerly RCW 39.10.061.]

Notes: Sunset Act application: See note following chapter digest.

Effective date -- 2002 c 46: See note following RCW 39.10.300.

Effective date -- 2001 c 328: See note following RCW 39.10.210.

State Codes and Statutes

Statutes > Washington > Title-39 > 39-10 > 39-10-340

General contractor/construction manager procedure — Uses.

Subject to the process in RCW 39.10.270 or 39.10.280, public bodies may utilize the general contractor/construction manager procedure for public works projects where:

     (1) Implementation of the project involves complex scheduling, phasing, or coordination;

     (2) The project involves construction at an occupied facility which must continue to operate during construction;

     (3) The involvement of the general contractor/construction manager during the design stage is critical to the success of the project;

     (4) The project encompasses a complex or technical work environment; or

     (5) The project requires specialized work on a building that has historic significance.

[2007 c 494 § 301. Prior: 2003 c 352 § 3; 2003 c 300 § 5; 2002 c 46 § 2; 2001 c 328 § 3. Formerly RCW 39.10.061.]

Notes: Sunset Act application: See note following chapter digest.

Effective date -- 2002 c 46: See note following RCW 39.10.300.

Effective date -- 2001 c 328: See note following RCW 39.10.210.


State Codes and Statutes

State Codes and Statutes

Statutes > Washington > Title-39 > 39-10 > 39-10-340

General contractor/construction manager procedure — Uses.

Subject to the process in RCW 39.10.270 or 39.10.280, public bodies may utilize the general contractor/construction manager procedure for public works projects where:

     (1) Implementation of the project involves complex scheduling, phasing, or coordination;

     (2) The project involves construction at an occupied facility which must continue to operate during construction;

     (3) The involvement of the general contractor/construction manager during the design stage is critical to the success of the project;

     (4) The project encompasses a complex or technical work environment; or

     (5) The project requires specialized work on a building that has historic significance.

[2007 c 494 § 301. Prior: 2003 c 352 § 3; 2003 c 300 § 5; 2002 c 46 § 2; 2001 c 328 § 3. Formerly RCW 39.10.061.]

Notes: Sunset Act application: See note following chapter digest.

Effective date -- 2002 c 46: See note following RCW 39.10.300.

Effective date -- 2001 c 328: See note following RCW 39.10.210.