Marine beach front protective bulkheads or rockwalls.

(1) In order to protect the property of marine waterfront shoreline owners it is necessary to facilitate issuance of permits for bulkheads or rockwalls under certain conditions.

     (2) The department shall issue a permit with or without conditions within forty-five days of receipt of a complete and accurate application which authorizes commencement of construction, replacement, or repair of a marine beach front protective bulkhead or rockwall for single-family type residences or property under the following conditions:

     (a) The waterward face of a new bulkhead or rockwall shall be located only as far waterward as is necessary to excavate for footings or place base rock for the structure and under no conditions shall be located more than six feet waterward of the ordinary high water line;

     (b) Any bulkhead or rockwall to replace or repair an existing bulkhead or rockwall shall be placed along the same alignment as the bulkhead or rockwall it is replacing. However, the replaced or repaired bulkhead or rockwall may be placed waterward of and directly abutting the existing structure only in cases where removal of the existing bulkhead or rockwall would result in environmental degradation or removal problems related to geological, engineering, or safety considerations; and

     (c) Construction of a new bulkhead or rockwall, or replacement or repair of an existing bulkhead or rockwall waterward of the existing structure shall not result in the permanent loss of critical food fish or shellfish habitats; and

     (d) Timing constraints shall be applied on a case-by-case basis for the protection of critical habitats, including but not limited to migration corridors, rearing and feeding areas, and spawning habitats, for the proper protection of fish life.

     (3) Any bulkhead or rockwall construction, replacement, or repair not meeting the conditions in this section shall be processed under this chapter in the same manner as any other application.

     (4) Any person aggrieved by the approval, denial, conditioning, or modification of a permit under this section may appeal the decision as provided in RCW 77.55.021(4).

[2010 c 210 § 28; 2005 c 146 § 501; 1991 c 279 § 1. Formerly RCW 77.55.200, 75.20.160.]

Notes: Intent -- Effective dates -- Application -- Pending cases and rules -- 2010 c 210: See notes following RCW 43.21B.001.

Part headings not law -- 2005 c 146: See note following RCW 77.55.011.

State Codes and Statutes

Statutes > Washington > Title-77 > 77-55 > 77-55-141

Marine beach front protective bulkheads or rockwalls.

(1) In order to protect the property of marine waterfront shoreline owners it is necessary to facilitate issuance of permits for bulkheads or rockwalls under certain conditions.

     (2) The department shall issue a permit with or without conditions within forty-five days of receipt of a complete and accurate application which authorizes commencement of construction, replacement, or repair of a marine beach front protective bulkhead or rockwall for single-family type residences or property under the following conditions:

     (a) The waterward face of a new bulkhead or rockwall shall be located only as far waterward as is necessary to excavate for footings or place base rock for the structure and under no conditions shall be located more than six feet waterward of the ordinary high water line;

     (b) Any bulkhead or rockwall to replace or repair an existing bulkhead or rockwall shall be placed along the same alignment as the bulkhead or rockwall it is replacing. However, the replaced or repaired bulkhead or rockwall may be placed waterward of and directly abutting the existing structure only in cases where removal of the existing bulkhead or rockwall would result in environmental degradation or removal problems related to geological, engineering, or safety considerations; and

     (c) Construction of a new bulkhead or rockwall, or replacement or repair of an existing bulkhead or rockwall waterward of the existing structure shall not result in the permanent loss of critical food fish or shellfish habitats; and

     (d) Timing constraints shall be applied on a case-by-case basis for the protection of critical habitats, including but not limited to migration corridors, rearing and feeding areas, and spawning habitats, for the proper protection of fish life.

     (3) Any bulkhead or rockwall construction, replacement, or repair not meeting the conditions in this section shall be processed under this chapter in the same manner as any other application.

     (4) Any person aggrieved by the approval, denial, conditioning, or modification of a permit under this section may appeal the decision as provided in RCW 77.55.021(4).

[2010 c 210 § 28; 2005 c 146 § 501; 1991 c 279 § 1. Formerly RCW 77.55.200, 75.20.160.]

Notes: Intent -- Effective dates -- Application -- Pending cases and rules -- 2010 c 210: See notes following RCW 43.21B.001.

Part headings not law -- 2005 c 146: See note following RCW 77.55.011.


State Codes and Statutes

State Codes and Statutes

Statutes > Washington > Title-77 > 77-55 > 77-55-141

Marine beach front protective bulkheads or rockwalls.

(1) In order to protect the property of marine waterfront shoreline owners it is necessary to facilitate issuance of permits for bulkheads or rockwalls under certain conditions.

     (2) The department shall issue a permit with or without conditions within forty-five days of receipt of a complete and accurate application which authorizes commencement of construction, replacement, or repair of a marine beach front protective bulkhead or rockwall for single-family type residences or property under the following conditions:

     (a) The waterward face of a new bulkhead or rockwall shall be located only as far waterward as is necessary to excavate for footings or place base rock for the structure and under no conditions shall be located more than six feet waterward of the ordinary high water line;

     (b) Any bulkhead or rockwall to replace or repair an existing bulkhead or rockwall shall be placed along the same alignment as the bulkhead or rockwall it is replacing. However, the replaced or repaired bulkhead or rockwall may be placed waterward of and directly abutting the existing structure only in cases where removal of the existing bulkhead or rockwall would result in environmental degradation or removal problems related to geological, engineering, or safety considerations; and

     (c) Construction of a new bulkhead or rockwall, or replacement or repair of an existing bulkhead or rockwall waterward of the existing structure shall not result in the permanent loss of critical food fish or shellfish habitats; and

     (d) Timing constraints shall be applied on a case-by-case basis for the protection of critical habitats, including but not limited to migration corridors, rearing and feeding areas, and spawning habitats, for the proper protection of fish life.

     (3) Any bulkhead or rockwall construction, replacement, or repair not meeting the conditions in this section shall be processed under this chapter in the same manner as any other application.

     (4) Any person aggrieved by the approval, denial, conditioning, or modification of a permit under this section may appeal the decision as provided in RCW 77.55.021(4).

[2010 c 210 § 28; 2005 c 146 § 501; 1991 c 279 § 1. Formerly RCW 77.55.200, 75.20.160.]

Notes: Intent -- Effective dates -- Application -- Pending cases and rules -- 2010 c 210: See notes following RCW 43.21B.001.

Part headings not law -- 2005 c 146: See note following RCW 77.55.011.